Advertisement
Products & Newsletters
Tower Light Alarm Circuit
Accurate tower light monitoring is a serious matter, and great care
can be taken to install a thorough and automatic monitoring system.
Designing a system to provide a single-lamp failure can quickly fill
several status channels on a facility's transmitter remote control
system if one status input is dedicated to each lamp monitor circuit.
Here is a method to spare the extra status channels and instead use a
single telemtry channel to provide the same level of lamp
resolution.
This pseudo-binary system uses a series of diodes and relay contacts to
vary the indicated voltage. The parts needed:
1K, 1W resistor
12vdc power supply
7 diodes, 1N4005 are used here
3 SSAC tower light monitor modules
The SSAC tower
light monitor modules have floating form C relay contacts. These are
installed so that the relay contacts are closed when the lights are
off. The 1N4005 diodes have higher reverse-voltage and forward-current
ratings than this circuit requires, but because they are so
inexpensive, the higher ratings provide additional insurance against
failure.
The relay contacts in the diagram are connected as follows:
S1 - Top beacon
S2 - Center beacon
S3 - Side markers
Because the voltage drop across the diode junction is 0.7 volts, the
resulting output voltage of the circuit can easily identify which
lights are on or off. When all the tower lights are off, the circuit
output is zero volts. When only the side lights are on, the circuit
output is 0.7 volts. When only the center beacon is on, the circuit
output is 1.4 volts. When only the top beacon is on, the circuit output
2.8 volts.
Because the diodes and switches are in series, the voltages will add if
more than one relay is open. Calibrate the remote control telemetry
input for any desired multiplication factor. A handy reference in this
example would be to set an input voltage of 0.7 volts to provide a
100mv reading. With this, the resulting telemetry readings based on the
lamp condition would be:
0 Volts = All Lights OFF
100 = side lights ON, both beacons OUT
200 = center beacon ON, top beacon and side lights OUT
300 = side lights and center beacon ON, top beacon OUT
400 = top beacon ON, center beacon and side lights OUT
500 = top beacon and side lights ON, center beacon OUT
600 = top beacon and center beacon ON, side lights OUT
700 = All lights ON
These divisions can also be used to set various alarm levels to
indicate a lamp failure. If the reading drops below 650 but stays above
550, a single side marker is out. The FCC and FAA do not require
notification of a single side marker, so this would be a warning
indicator. However, if the reading drops below 550, a more serious
alarm can be set because at least one beacon has failed.
This diode-string scheme could be continued with more switches and sets
of diodes, but the next step would be require 8 diodes, and then 16
diodes and so on. This can quickly get out of hand. In an instance
where more than 4 levels of metering are required, reverse-biased zener
diodes would be a better choice.
Moates operates Loud and Clean, a company that designs, installs, optimizes and maintains radio broadcast antenna systems, transmission facilities, audio processing systems, digital storage and production facilities and studio architecture and acoustics. He is based in the Boston area. Reach him through http://www.loudandclean.com
Want to use this article? Click here for options!
© 2008 Penton Media Inc.
Webinars
Critical Aspects of Tower Site Safety
Learn the steps you can take to ensure a safe working environment at a tower site.
33 1/3 Things You Forgot
Think wire is just wire? Think again.
Advertisement
Podcast Archives
Radio Currents Podcast, Oct 6
The House passes the Webcaster Settlement Act, another House bills looks to require HD Radio in all radio receivers, and the NAB Radio Show announces attendance figures.
Radio Currents Podcast, Sep 29
The FCC accepts method modeling for AM directionals, a CAP profile for EAS devices is released, the NRSC posts reports, and Rick Rapalee is named the DOE for Entercom Sacramento.
Blog
Talkback: The Radio Blog
Talkback, the Radio magazine blog, is your chance to post and comment on technical issues in radio.
Projects in Progress
Projects in Progress tracks facility installation projects from start to finish. Follow the progress of the WUVT-FM transmitter site upgrade.
Today in Radio History
Milestones From Radio's Past
The history of radio broadcasting extends beyond the work of a few famous inventors.
Current Issue
Clean up the Audio
Advancement of codec design has allowed lower bit-rates to be employed, and most codecs sound decent at these rates, but they are much more fragile with regards to distortion and susceptible to artifacts.






